Garrison Creek has pushed hard in Q3 /Q4 to get the house completed for us. Drywall started to go up in late August after the electricians, plumbers and tilers did their rough installations. Paint and trim soon followed as well as the kitchen and bathroom cabinet installations.
All of it came together on December 23, 2020 when we received our occupancy permit (Merry Christmas to us!).
Thanks to Kyle and Fraser at Garrison and the many tradespeople who help us get to this point, despite a crazy year due to COVID-19.
What’s Ahead
We move in!